The initial idea for the layout in February 2022.March – Inner loop is complete and wagon siding and goods shed roads are laid.April – Ballasting of track started and track for local trains into the station laid.May – Illuminated Engine ShedCliff face by wagon siding under construction.June – Goods Yard and Coal Merchant.Town building planJuly – Details added to Goods Yard, cliff faces painted and top of hill now has greenery.August – Rock wall, planting details and culvert added at the end of the wagon sidings.Additional tracks laid in station area.September – Church built and sited.First row of shops completed.October – Mine sidings laid and incline base put down for outer two circular tracks.Signal BoxNovember – Main platform sited.December – Detailing added to church and static grass added to lineside.